|
|
Hi all,I have a few questions on welding, hope Ill have some help from here.I have 3 rectangular steel blocks each about 17m X 0.4m X 0.2m. They are to be welded at the 0.4m X 0.2m face, forming a straight line. They joints formed between blocks are a narrow gap joint with an 11mm gap. SAW method would be used as the welding method. It would resemble this:__________ __________ __________I would like to know is that, upon completion of welding for these joints, how long must I wait before I can move the entire welded blocks? I understand that to prevent hydrogen cracking, typically 3 days are required for cooling. As these blocks will be on a jig during welding, upon completion of it, I want to free the use of the jig, hence Im wondering if it is possible if I can move the entire welded block during these 3 days of cooling to some other place and allow the cooling to take place while I can use the jig to perform another set of welding.Also, would the lifting cause any distortion to the straightness of the blocks?Id really appreciate for any help I can receive from here. Thank you
Reply:Those blocks are HUGE! What are they being used for?
Reply:Most warpage happens in the cooling phase over a period of time but if these pieces are held in a jig during welding will likely cause internal stresses that can lead to cracking because they are restrained and have no way to expand and contract from the heating and cooling. You may need to monitor preheat and interpass temperatures for such heavy plate. I think if the pieces get down to a temperature where you could quickly touch them (300-400 deg's ?) you'd be OK to move them. You may have to stress relief them which requires even more heat. It would help to know what they are for?
Reply:Hi @shortfuse and @Welder Dave, They're mainly used for support in a vertical position like this: | | |@Welder Dave, with regards to the internal stresses due to it being restrained by the jig, its a valid concern, but in this case, measures have been taken care of that issue. After the welding is completed, a post weld heat treatment would be carried out for an hour at 150 degC. After which, an insulation blanket is used to cover the weld joint, protecting the joint from the outdoors environment. The joint will be covered for about 3 days. Typically, the preheat and interpass temperatures do not exceed 200 degC. @welder Dave, may i know which unit of temperature you are referring to?
Reply:3 days seems like a long time, I would bet you could pull it out of PWHT and set it on some stickers, cover it up with whatever you are going to use and free up the jigExperience is something you get right after you need it
Reply:If you are using SAW and proper preheat/post heat then hydrogen should not be a problem. Like Welder Dave said once they are cooled down to around 300 it is all over and handling is not going to change what you have. A post weld treatment at even 150 C would not do anything unless you have created a hydrogen problem by not using a low hydrogen process and needed more time to release hydrogen. On that thickness it is not going to cool very quickly so remove from fixture once black , wrap up in blankets of kaowool and let it sit. Insulating the joint would keep it up in the 150 C range for many hours. I find it odd that your measurements are in metres. No one in my experience deals with metres... only millimeters. No confusion. It sounds like you are splicing flanges for welded beams. You are not going to cause any bending or distortion when handling hot as long as it is black and you use spreader bars and at least two cranes.
Reply:I was talking Fahrenheit and I don't think 150C is enough heat to remove any stresses. Stress relieving is usually over 1000F. What exactly are making supports for? It's hard to give very specific advice when we're guessing what you're trying to do.
Reply:How are you going to move it? It's about 150 feet long
Reply:@Welder Dave,These structures are the legs of the jackup rig. As these legs are too long (almost 500ft) to be fabricated at one go, they are split into section lengths (about 150ft per section) Each section is previously joined from smaller lengths of about 50ft and 30ft. So i'm looking into the welding of 3 smaller lengths (2 joints) together. The welded lengths would be about 140ft. The SAW process is a multipass welding process. @lotechman, may i know what you meant by "as long as it is black"?@Rock knocker, gantry cranes or tandem lifting by crawler cranes would be good enough for lifting.
Reply:By "black" he means at black heat. Hot, but not hot enough to have even a hint of dull red in very low light."USMCPOP" First-born son: KIA Iraq 1/26/05Syncrowave 250 w/ Coolmate 3Dialarc 250, Idealarc 250SP-175 +Firepower TIG 160S (gave the TA 161 STL to the son)Lincwelder AC180C (1952)Victor & Smith O/A torchesMiller spot welder
Reply:Sub-Arc is a hot fast process. Are there no welding engineers involved in this project? If your sub-arc is all done from one side and the pieces are restrained in a jig to keep them flat, you can be sure there's going to be a lot of built up stress. You'd almost have to fit them in a pre-bent position and they would contract and pull straight while cooling. It's probably not practical but welding from both sides would be another option to lessen built up stresses.
Reply:I would like to see some pictures of this jackup rig and the legs you are welding together in 3 separate sections.... I cant tell you anything by you displaying Lines like |
|